Please use this identifier to cite or link to this item:
http://acervodigital.unesp.br/handle/11449/76085
- Title:
- Risk/investment-driven transmission expansion planning with multiple scenarios
- Universidade Estadual Paulista (UNESP)
- 1751-8687
- This study presents a new methodology based on risk/investment to solve transmission network expansion planning (TNEP) problem with multiple future scenarios. Three mathematical models related to TNEP problems considering multiple future generation and load scenarios are also presented. These models will provide planners with a meaningful risk assessment that enable them to determine the necessary funding for transmission lines at a permissible risk level. The results using test and real systems show that the proposed method presents better solutions compared with scenario analysis method. ©The Institution of Engineering and Technology 2013.
- 31-Jul-2013
- IET Generation, Transmission and Distribution, v. 7, n. 2, p. 154-165, 2013.
- 154-165
- Future generations
- Real systems
- Risk levels
- Scenario analysis
- Transmission expansion planning
- Transmission network expansion planning
- Mathematical models
- Risk assessment
- http://dx.doi.org/10.1049/iet-gtd.2011.0742
- Acesso restrito
- outro
- http://repositorio.unesp.br/handle/11449/76085
There are no files associated with this item.
Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.